Integrated Power Development Scheme (IPDS)
  • The Government of India has launched a scheme i.e. IPDS for Strengthening of Sub-Transmission & Distribution Network and Metering in Urban areas.
  • M/s. PFC Ltd. (Power Finance Corporation), New Delhi is the Nodal Agency.
  • M/s. PFC Ltd. has communicated sanctions as: In 1st Phase, 3Nos. DPRs covering 15Nos. Towns in 3 Circles i.e. Vizianagaram(4 Towns), Visakhapatnam(3 Towns) and Eluru(8 Towns) for an amount of Rs.222.42 Crs. were sanctioned on 26.2.2015. In 2nd Phase, 2Nos. DPRs covering 14Towns in 2 Circles i.e., Srikakulam (5Towns) and Rajamahendravaram (9 Towns) for an amount of Rs.77.58Crs. were sanctioned on 09.03.2016.
  • M/s. PFC Ltd., New Delhi has sanctioned a DPR on 21.11.2017 for Implementation of Additional System Strengthening works under IPDS in 8 Towns for an amount of Rs.18.00 Crs. in addition to the above sanctions. Tenders were floated with due date of opening is 31.01.2018.
  • As per the scheme guidelines, M/s. PFCCL, New Delhi has appointed as PMA on 18.05.2015.
  • The Circle-wise sanctioned Scheme cost to APEPDCL is as shown below:

(Rs.in Crores)

Sl. No. Circle Sanctioned amount Govt. of India (GoI) Grant Addl. Sanction Amount
Grant for Scheme PMA (0.5% of approved DPR cost) Total Grant
1st PHASE
1 Vizianagaram 34.11 20.47 0.17 20.64 2.78
2 Visakhapatnam 118.69 71.21 0.59 71.80 4.43
3 West Godavari 69.62 41.77 0.35 42.12 5.00
Sub Total 222.42 133.45 1.11 134.57
2nd PHASE
1 Srikakulam 22.14 13.28 0.11 13.39 0.97
2 East Godavari 55.45 33.27 0.28 33.54 4.82
Sub Total 77.58 46.55 0.39 46.94

IPDS - PROGRESS OF WORKS IN APEPDCL (29 TOWNS) AS ON 31.01.2018

SL.No Name of the Work Unit Sanctioned Target (Awarded Quantity) Achieved (Completed Quantity) % of progress
1 New 33/11KV Indoor/Outdoor Sub-stations Nos. 33 39 27 69%
2 Addl. 8/5MVA PTRs in exisitng 33/11KV Sub-stations Nos. 13 23 17 74%
3 Enhancement of PTRs in exisitng 33/11KV Sub-stations Nos. 25 32 18 56%
4 Erection of New DTRs Nos. 1207 1577 1108 70%
5 Enhancement of DTRs Nos. 1082 1173 908 77%
6 R&M of 33/11KV existing Sub-stations Nos. 58 59 31 53%
7 33KV New Feeders Kms 129.45 154.78 96.64 62%
8 33KV Feeder Reconductoring Kms 38.80 42.20 15.50 37%
9 33KV Bay Extension at EHV Nos. 0 1 0 0%
10 11KV New Feeders Kms 556.20 377.46 169.95 45%
11 11KV Feeder Reconductoring Kms 166.13 144.12 84.20 58%
12 LT AB Cable & 11KV Covered Conductor Kms 41.60 135.50 2.50 2%
13 11KV Bay Extension Nos. 5 4.03 2 50%
14 New LT Lines Kms 217.60 100.34 57.82 58%
15 LT Line Reconductoring Kms 152.24 117.24 44.86 38%
16 Capacitor Bank Nos. 29 29 10 34%
17 Feeder/DT Meters Nos. 2409 2400 824 34%
18 Consumer Meters Nos. 433948 559982 26386 5%
19 Solar Panels KWp 1236 1236 947 77%
20 R&M of DTR structures Nos. 4242 3229 2557 79%
21 Installation of Sign Boards Nos. 2378 2378 1054 44%
a At Prominent locations No.s 116 116 1 1%
b At Sub-stations Nos. 68 68 38 56%
c At DTRs Nos. 2194 2194 1015 46%

IPDS - PROGRESS OF WORKS IN SRIKAKULAM CIRCLE (5 TOWNS) UNDER 2nd PHASE AS ON 31.01.2018

SL.No Name of the Work Unit Sanctioned Target (Awarded Quantity) Achieved (Completed Quantity) % of progress
1 New 33/11KV Indoor/Outdoor Sub-stations Nos. 1 2 1 50%
2 Addl. 8/5MVA PTRs in exisitng 33/11KV Sub-stations Nos. 1 1 0 0%
3 Enhancement of PTRs in exisitng 33/11KV Sub-stations Nos. 1 1 1 100%
4 Erection of New DTRs Nos. 100 100 81 81%
5 Enhancement of DTRs Nos. 136 136 33 24%
6 R&M of 33/11KV existing Sub-stations Nos. 7 7 1 14%
7 33KV New Feeders Kms 7.00 7.00 4.80 69%
8 33KV Feeder Reconductoring Kms 0.00 0.00 0.00 0%
9 33KV Bay Extension at EHV Nos. 0 0 0 0%
10 11KV New Feeders Kms 68.00 59.00 11.60 20%
11 11KV Feeder Reconductoring Kms 18.00 18.00 0.00 0%
12 LT AB Cable & 11KV Covered Conductor Kms 4.00 26.00 0.00 0%
13 11KV Bay Extension Nos. 3 2 0 0%
14 New LT Lines Kms 10.02 10.02 4.20 42%
15 LT Line Reconductoring Kms 46.19 46.19 3.00 6%
16 Capacitor Bank Nos. 5 5 3 60%
17 Feeder/DT Meters Nos. 324 315 29 9%
18 Consumer Meters Nos. 45359 46156 1573 3%
19 Solar Panels KWp 124 124 124 100%
20 R&M of DTR structures Nos. 120 120 4 3%
21 Installation of Sign Boards Nos. 259 259 1 0%
a At Prominent locations No.s 20 20 0 0%
b At Sub-stations Nos. 3 3 1 33%
c At DTRs Nos. 236 236 0 0%

IPDS - PROGRESS OF WORKS IN VIZIANAGARAM CIRCLE (4 TOWNS) UNDER 1st PHASE AS ON 31.01.2018

SL.No Name of the Work Unit Sanctioned Target (Awarded Quantity) Achieved (Completed Quantity) % of progress
1 New 33/11KV Indoor/Outdoor Sub-stations Nos. 3 3 3 100%
2 Addl. 8/5MVA PTRs in exisitng 33/11KV Sub-stations Nos. 2 2 2 100%
3 Enhancement of PTRs in exisitng 33/11KV Sub-stations Nos. 2 2 2 100%
4 Erection of New DTRs Nos. 122 122 122 100%
5 Enhancement of DTRs Nos. 70 70 70 100%
6 R&M of 33/11KV existing Sub-stations Nos. 6 6 4 67%
7 33KV New Feeders Kms 13 16.90 16.90 100%
8 33KV Feeder Reconductoring Kms 4 3.00 3.00 100%
9 33KV Bay Extension at EHV Nos. 0 0 0 0%
10 11KV New Feeders Kms 75 47.55 41.29 87%
11 11KV Feeder Reconductoring Kms 55 10.00 10.00 100%
12 LT AB Cable & 11KV Covered Conductor Kms 3 30.50 2.50 8%
13 11KV Bay Extension Nos. 2 2 2 100%
14 New LT Lines Kms 30 10.00 3.70 37%
15 LT Line Reconductoring Kms 47 12.00 12.00 100%
16 Capacitor Bank Nos. 5 5 1 20%
17 Feeder/DT Meters Nos. 445 445 131 29%
18 Consumer Meters Nos. 40982 71963 473 1%
19 Solar Panels KWp 130 130 130 100%
20 R&M of DTR structures Nos. 534 686 673 98%
21 Installation of Sign Boards Nos. 215 215 117 54%
a At Prominent locations No.s 16 16 0 0%
b At Sub-stations Nos. 7 7 5 71%
c At DTRs Nos. 192 192 112 58%

IPDS - PROGRESS OF WORKS IN VISAKHAPATNAM CIRCLE (3 TOWNS) UNDER 1st PHASE AS ON 31.01.2018

SL.No Name of the Work Unit Sanctioned Target (Awarded Quantity) Achieved (Completed Quantity) % of progress
1 New 33/11KV Indoor/Outdoor Sub-stations Nos. 14 15 13 87%
2 Addl. 8/5MVA PTRs in exisitng 33/11KV Sub-stations Nos. 6 6 6 100%
3 Enhancement of PTRs in exisitng 33/11KV Sub-stations Nos. 8 15 8 53%
4 Erection of New DTRs Nos. 420 758 528 70%
5 Enhancement of DTRs Nos. 372 495 385 78%
6 R&M of 33/11KV existing Sub-stations Nos. 16 30 22 73%
7 33KV New Feeders Kms 45.00 53.88 32.95 61%
8 33KV Feeder Reconductoring Kms 0.00 0.00 0.00 0%
9 33KV Bay Extension at EHV Nos. 0 0 0 0%
10 11KV New Feeders Kms 237.00 114.80 78.30 68%
11 11KV Feeder Reconductoring Kms 5.00 1.90 1.90 100%
12 LT AB Cable & 11KV Covered Conductor Kms 11.00 50.00 0.00 0%
13 11KV Bay Extension Nos. 0 0 0 0%
14 New LT Lines Kms 119.00 40.00 40.00 100%
15 LT Line Reconductoring Kms 0.00 0.00 0.00 0%
16 Capacitor Bank Nos. 5 5 3 60%
17 Feeder/DT Meters Nos. 739 739 434 59%
18 Consumer Meters Nos. 107000 189762 21336 11%
19 Solar Panels KWp 418 418 278 67%
20 R&M of DTR structures Nos. 2665 1500 1239 83%
21 Installation of Sign Boards Nos. 1109 1109 812 73%
a At Prominent locations No.s 12 12 1 8%
b At Sub-stations Nos. 30 30 23 77%
c At DTRs Nos. 1067 1067 788 74%

IPDS - PROGRESS OF WORKS IN RAJAMAHENDRAVARAM CIRCLE (EAST GODAVARI DISTRICT) (9 TOWNS) UNDER 2nd PHASE AS ON 31.01.2018

SL.No Name of the Work Unit Sanctioned Target (Awarded Quantity) Achieved (Completed Quantity) % of progress
1 New 33/11KV Indoor/Outdoor Sub-stations Nos. 9 11 5 45%
2 Addl. 8/5MVA PTRs in exisitng 33/11KV Sub-stations Nos. 2 6 2 33%
3 Enhancement of PTRs in exisitng 33/11KV Sub-stations Nos. 11 11 4 36%
4 Erection of New DTRs Nos. 241 241 74 31%
5 Enhancement of DTRs Nos. 147 147 93 63%
6 R&M of 33/11KV existing Sub-stations Nos. 21 8 0 0%
7 33KV New Feeders Kms 29.00 31.10 6.80 22%
8 33KV Feeder Reconductoring Kms 21.20 21.20 0.00 0%
9 33KV Bay Extension at EHV Nos. 0 0 0 0%
10 11KV New Feeders Kms 97.13 97.13 4.90 5%
11 11KV Feeder Reconductoring Kms 16.22 16.22 3.20 20%
12 LT AB Cable & 11KV Covered Conductor Kms 0.00 0.00 0.00 0%
13 11KV Bay Extension Nos. 0 0 0 0%
14 New LT Lines Kms 20.32 20.32 0.00 0%
15 LT Line Reconductoring Kms 24.15 24.15 0.00 0%
16 Capacitor Bank Nos. 10 10 0 0%
17 Feeder/DT Meters Nos. 271 271 12 4%
18 Consumer Meters Nos. 103355 119969 1594 1%
19 Solar Panels KWp 331 331 182 55%
20 R&M of DTR structures Nos. 400 400 144 36%
21 Installation of Sign Boards Nos. 72 72 4 6%
a At Prominent locations No.s 36 36 0 0%
b At Sub-stations Nos. 18 18 4 22%
c At DTRs Nos. 18 18 0 0%

IPDS - PROGRESS OF WORKS IN ELURU CIRCLE (WEST GODAVARI DISTRICT) (8 TOWNS) UNDER 1st PHASE AS ON 31.01.2018

SL.No Name of the Work Unit Sanctioned Target (Awarded Quantity) Achieved (Completed Quantity) % of progress
1 New 33/11KV Indoor/Outdoor Sub-stations Nos. 6 8 5 63%
2 Addl. 8/5MVA PTRs in exisitng 33/11KV Sub-stations Nos. 2 8 7 88%
3 Enhancement of PTRs in exisitng 33/11KV Sub-stations Nos. 3 3 3 100%
4 Erection of New DTRs Nos. 324 356 303 85%
5 Enhancement of DTRs Nos. 357 325 327 101%
6 R&M of 33/11KV existing Sub-stations Nos. 8 8 4 50%
7 33KV New Feeders Kms 35.45 45.90 35.19 77%
8 33KV Feeder Reconductoring Kms 13.60 18.00 12.50 69%
9 33KV Bay Extension at EHV Nos. 0 1 0 0%
10 11KV New Feeders Kms 79.07 58.98 33.86 57%
11 11KV Feeder Reconductoring Kms 71.91 98.00 69.10 71%
12 LT AB Cable & 11KV Covered Conductor Kms 23.60 29.00 0.00 0%
13 11KV Bay Extension Nos. 0 0 0 0%
14 New LT Lines Kms 38.26 20.00 9.92 50%
15 LT Line Reconductoring Kms 34.90 34.90 29.86 86%
16 Capacitor Bank Nos. 4 4 3 75%
17 Feeder/DT Meters Nos. 630 630 218 35%
18 Consumer Meters Nos. 137252 132132 1410 1%
19 Solar Panels KWp 233 233 233 100%
20 R&M of DTR structures Nos. 523 523 497 95%
21 Installation of Sign Boards Nos. 723 723 120 17%
a At Prominent locations No.s 32 32 0 0%
b At Sub-stations Nos. 10 10 5 50%
c At DTRs Nos. 681 681 115 71%