Integrated Power Development Scheme (IPDS)

  • The Government of India has launched a scheme i.e. IPDS for Strengthening of Sub-Transmission & Distribution Network and Metering in Urban areas.
  • M/s. PFC Ltd. (Power Finance Corporation), New Delhi is the Nodal Agency.
  • M/s. PFC Ltd. has communicated sanctions as: In 1st Phase, 3Nos. DPRs covering 15Nos. Towns in 3 Circles i.e. Vizianagaram(4 Towns), Visakhapatnam(3 Towns) and Eluru(8 Towns) for an amount of Rs.222.42 Crs. were sanctioned on 26.2.2015. In 2nd Phase, 2Nos. DPRs covering 14Towns in 2 Circles i.e., Srikakulam (5Towns) and Rajamahendravaram (9 Towns) for an amount of Rs.77.58Crs. were sanctioned on 09.03.2016.
  • M/s. PFC Ltd., New Delhi has sanctioned a DPR on 21.11.2017 for Implementation of Additional System Strengthening works under IPDS in 8 Towns for an amount of Rs.18.00 Crs. in addition to the above sanctions. Tenders were floated with due date of opening is 31.01.2018.
  • As per the scheme guidelines, M/s. PFCCL, New Delhi has appointed as PMA on 18.05.2015.
  • The Circle-wise sanctioned Scheme cost to APEPDCL is as shown below:
(Rs. in Crores)
Sl. No. Circle Sanctioned amount   Addl. Sanction Amount
Govt. of India (GoI) Grant
Grant for Scheme PMA (0.5% of approved DPR cost) Total Grant
  1st PHASE          
1 Vizianagaram 34.11 20.47 0.17 20.64 2.78
2 Visakhapatnam 118.69 71.21 0.59 71.80 4.43
3 West Godavari 69.62 41.77 0.35 42.12 5.00
  Sub Total 222.42 133.45 1.11 134.57  
  2st PHASE          
1 Srikakulam 22.14 13.28 0.11 13.39 0.97
2 East Godavari 55.45 33.27 0.28 33.54 4.82
  Sub Total 77.58 46.55 0.39 46.94  
  Grand Total 300.01 180.00 1.50 181.50 18.00

IPDS - PROGRESS OF WORKS IN APEPDCL (29 TOWNS) AS ON 31.01.2018

Sl. No Name of the Work Unit Sanctioned Target (Awarded Quantity) Achieved (Completed Quantity) % of progress
1 New 33/11KV Indoor/Outdoor Sub-stations Nos. 33 39 27 69%
2 Addl. 8/5MVA PTRs in exisitng 33/11KV Sub-stations Nos. 13 23 17 74%
3 Enhancement of PTRs in exisitng 33/11KV Sub-stations Nos. 25 32 18 56%
4 Erection of New DTRs Nos. 1207 1577 1108 70%
5 Enhancement of DTRs Nos. 1082 1173 908 77%
6 R&M of 33/11KV existing Sub-stations Nos. 58 59 31 53%
7 33KV New Feeders Kms 129.45 154.78 96.64 62%
8 33KV Feeder Reconductoring Kms 38.80 42.20 15.50 37%
9 33KV Bay Extension at EHV Nos. 0 1 0 0%
10 11KV New Feeders Kms 556.20 377.46 169.95 45%
11 11KV Feeder Reconductoring Kms 166.13 144.12 84.20 58%
12 LT AB Cable & 11KV Covered Conductor Kms 41.60 135.50 2.50 2%
13 11KV Bay Extension Nos. 5 4.03 2 50%
14 New LT Lines Kms 217.60 100.34 57.82 58%
15 LT Line Reconductoring Kms 152.24 117.24 44.86 38%
16 Capacitor Bank Nos. 29 29 10 34%
17 Feeder/DT Meters Nos. 2409 2400 824 34%
18 Consumer Meters Nos. 433948 559982 26386 5%
19 Solar Panels KWp 1236 1236 947 77%
20 R&M of DTR structures Nos. 4242 3229 2557 79%
21 Installation of Sign Boards Nos. 2378 2378 1054 44%
a At Prominent locations Nos. 116 116 1 1%
b At Sub-stations Nos. 68 68 38 56%
c At DTRs Nos. 2194 2194 1015 46%

IPDS - PROGRESS OF WORKS IN SRIKAKULAM CIRCLE (5 TOWNS) UNDER 2nd PHASE AS ON 31.01.2018

Sl. No Name of the Work Unit Sanctioned Target (Awarded Quantity) Achieved (Completed Quantity) % of progress
1 New 33/11KV Indoor/Outdoor Sub-stations Nos. 1 2 1 50%
2 Addl. 8/5MVA PTRs in exisitng 33/11KV Sub-stations Nos. 1 1 0 0%
3 Enhancement of PTRs in exisitng 33/11KV Sub-stations Nos. 1 1 1 100%
4 Erection of New DTRs Nos. 100 100 81 81%
5 Enhancement of DTRs Nos. 136 136 33 24%
6 R&M of 33/11KV existing Sub-stations Nos. 7 7 1 14%
7 33KV New Feeders Kms 7.00 7.00 4.80 69%
8 33KV Feeder Reconductoring Kms 0.00 0.00 0.00 0%
9 33KV Bay Extension at EHV Nos. 0 0 0 0%
10 11KV New Feeders Kms 68.00 59.00 11.60 20%
11 11KV Feeder Reconductoring Kms 18.00 18.00 0.00 0%
12 LT AB Cable & 11KV Covered Conductor Kms 4.00 26.00 0.00 0%
13 11KV Bay Extension Nos. 3 2 0 0%
14 New LT Lines Kms 10.02 10.02 4.20 42%
15 LT Line Reconductoring Kms 46.19 46.19 3.00 6%
16 Capacitor Bank Nos. 5 5 3 60%
17 Feeder/DT Meters Nos. 324 315 29 9%
18 Consumer Meters Nos. 45359 46156 1573 3%
19 Solar Panels KWp 124 124 124 100%
20 R&M of DTR structures Nos. 120 120 4 3%
21 Installation of Sign Boards Nos. 259 259 1 0%
a At Prominent locations Nos. 20 20 0 0%
b At Sub-stations Nos. 3 3 1 33%
c At DTRs Nos. 236 236 0 0%

IPDS - PROGRESS OF WORKS IN VIZIANAGARAM CIRCLE (4 TOWNS) UNDER 1st PHASE AS ON 31.01.2018

Sl. No Name of the Work Unit Sanctioned Target (Awarded Quantity) Achieved (Completed Quantity) % of progress
1 New 33/11KV Indoor/Outdoor Sub-stations Nos. 3 3 3 100%
2 Addl. 8/5MVA PTRs in exisitng 33/11KV Sub-stations Nos. 2 2 2 100%
3 Enhancement of PTRs in exisitng 33/11KV Sub-stations Nos. 2 2 2 100%
4 Erection of New DTRs Nos. 122 122 122 100%
5 Enhancement of DTRs Nos. 70 70 70 100%
6 R&M of 33/11KV existing Sub-stations Nos. 6 6 4 67%
7 33KV New Feeders Kms 13 16.90 16.90 100%
8 33KV Feeder Reconductoring Kms 4 3.00 3.00 100%
9 33KV Bay Extension at EHV Nos. 0 0 0 0%
10 11KV New Feeders Kms 75 47.55 41.29 87%
11 11KV Feeder Reconductoring Kms 55 10.00 10.00 100%
12 LT AB Cable & 11KV Covered Conductor Kms 3 30.50 2.50 8%
13 11KV Bay Extension Nos. 2 2 2 100%
14 New LT Lines Kms 30 10.00 3.70 37%
15 LT Line Reconductoring Kms 47 12.00 12.00 100%
16 Capacitor Bank Nos. 5 5 1 20%
17 Feeder/DT Meters Nos. 445 445 131 29%
18 Consumer Meters Nos. 40982 71963 473 1%
19 Solar Panels KWp 130 130 130 100%
20 R&M of DTR structures Nos. 534 686 673 98%
21 Installation of Sign Boards Nos. 215 215 117 54%
a At Prominent locations Nos. 16 16 0 0%
b At Sub-stations Nos. 7 7 5 71%
c At DTRs Nos. 192 192 112 58%

IPDS - PROGRESS OF WORKS IN VISAKHAPATNAM CIRCLE (3 TOWNS) UNDER 1st PHASE AS ON 31.01.2018

Sl. No Name of the Work Unit Sanctioned Target (Awarded Quantity) Achieved (Completed Quantity) % of progress
1 New 33/11KV Indoor/Outdoor Sub-stations Nos. 14 15 13 87%
2 Addl. 8/5MVA PTRs in exisitng 33/11KV Sub-stations Nos. 6 6 6 100%
3 Enhancement of PTRs in exisitng 33/11KV Sub-stations Nos. 8 15 8 53%
4 Erection of New DTRs Nos. 420 758 528 70%
5 Enhancement of DTRs Nos. 372 495 385 78%
6 R&M of 33/11KV existing Sub-stations Nos. 16 30 22 73%
7 33KV New Feeders Kms 45.00 53.88 32.95 61%
8 33KV Feeder Reconductoring Kms 0.00 0.00 0.00 0%
9 33KV Bay Extension at EHV Nos. 0 0 0 0%
10 11KV New Feeders Kms 237.00 114.80 78.30 68%
11 11KV Feeder Reconductoring Kms 5.00 1.90 1.90 100%
12 LT AB Cable & 11KV Covered Conductor Kms 11.00 50.00 0.00 0%
13 11KV Bay Extension Nos. 0 0 0 0%
14 New LT Lines Kms 119.00 40.00 40.00 100%
15 LT Line Reconductoring Kms 0.00 0.00 0.00 0%
16 Capacitor Bank Nos. 5 5 3 60%
17 Feeder/DT Meters Nos. 739 739 434 59%
18 Consumer Meters Nos. 107000 189762 21336 11%
19 Solar Panels KWp 418 418 278 67%
20 R&M of DTR structures Nos. 2665 1500 1239 83%
21 Installation of Sign Boards Nos. 1109 1109 812 73%
a At Prominent locations Nos. 12 12 1 8%
b At Sub-stations Nos. 30 30 23 77%
c At DTRs Nos. 1067 1067 788 74%

IPDS - PROGRESS OF WORKS IN RAJAMAHENDRAVARAM CIRCLE (EAST GODAVARI DISTRICT) (9 TOWNS) UNDER 2nd PHASE AS ON 31.01.2018

Sl. No Name of the Work Unit Sanctioned Target (Awarded Quantity) Achieved (Completed Quantity) % of progress
1 New 33/11KV Indoor/Outdoor Sub-stations Nos. 9 11 5 45%
2 Addl. 8/5MVA PTRs in exisitng 33/11KV Sub-stations Nos. 2 6 2 33%
3 Enhancement of PTRs in exisitng 33/11KV Sub-stations Nos. 11 11 4 36%
4 Erection of New DTRs Nos. 241 241 74 31%
5 Enhancement of DTRs Nos. 147 147 93 63%
6 R&M of 33/11KV existing Sub-stations Nos. 21 8 0 0%
7 33KV New Feeders Kms 29.00 31.10 6.80 22%
8 33KV Feeder Reconductoring Kms 21.20 21.20 0.00 0%
9 33KV Bay Extension at EHV Nos. 0 0 0 0%
10 11KV New Feeders Kms 97.13 97.13 4.90 5%
11 11KV Feeder Reconductoring Kms 16.22 16.22 3.20 20%
12 LT AB Cable & 11KV Covered Conductor Kms 0.00 0.00 0.00 0%
13 11KV Bay Extension Nos. 0 0 0 0%
14 New LT Lines Kms 20.32 20.32 0.00 0%
15 LT Line Reconductoring Kms 24.15 24.15 0.00 0%
16 Capacitor Bank Nos. 10 10 0 0%
17 Feeder/DT Meters Nos. 271 271 12 4%
18 Consumer Meters Nos. 103355 119969 1594 1%
19 Solar Panels KWp 331 331 182 55%
20 R&M of DTR structures Nos. 400 400 144 36%
21 Installation of Sign Boards Nos. 72 72 4 6%
a At Prominent locations Nos. 36 36 0 0%
b At Sub-stations Nos. 18 18 4 22%
c At DTRs Nos. 18 18 0 0%

 

IPDS - PROGRESS OF WORKS IN ELURU CIRCLE (WEST GODAVARI DISTRICT) (8 TOWNS) UNDER 1st PHASE AS ON 31.01.2018

Sl. No Name of the Work Unit Sanctioned Target (Awarded Quantity) Achieved (Completed Quantity) % of progress
1 New 33/11KV Indoor/Outdoor Sub-stations Nos. 6 8 5 63%
2 Addl. 8/5MVA PTRs in exisitng 33/11KV Sub-stations Nos. 2 8 7 88%
3 Enhancement of PTRs in exisitng 33/11KV Sub-stations Nos. 3 3 3 100%
4 Erection of New DTRs Nos. 324 356 303 85%
5 Enhancement of DTRs Nos. 357 325 327 101%
6 R&M of 33/11KV existing Sub-stations Nos. 8 8 4 50%
7 33KV New Feeders Kms 35.45 45.90 35.19 77%
8 33KV Feeder Reconductoring Kms 13.60 18.00 12.50 69%
9 33KV Bay Extension at EHV Nos. 0 1 0 0%
10 11KV New Feeders Kms 79.07 58.98 33.86 57%
11 11KV Feeder Reconductoring Kms 71.91 98.00 69.10 71%
12 LT AB Cable & 11KV Covered Conductor Kms 23.60 29.00 0.00 0%
13 11KV Bay Extension Nos. 0 0 0 0%
14 New LT Lines Kms 38.26 20.00 9.92 50%
15 LT Line Reconductoring Kms 34.90 34.90 29.86 86%
16 Capacitor Bank Nos. 4 4 3 75%
17 Feeder/DT Meters Nos. 630 630 218 35%
18 Consumer Meters Nos. 137252 132132 1410 1%
19 Solar Panels KWp 233 233 233 100%
20 R&M of DTR structures Nos. 523 523 497 95%
21 Installation of Sign Boards Nos. 723 723 120 17%
a At Prominent locations Nos. 32 32 0 0%
b At Sub-stations Nos. 10 10 5 50%
c At DTRs Nos. 681 681 115 17%