Name of the Project: Deen Dayal Upadhyaya Gram Jyothi Yojana (DDUGJY):

  • The Government of India has launched a Scheme i.e. DDUGJY for Electrification of Households, Strengthening of Sub-Transmission, Distribution Network and Metering in Rural Areas.
  • M/s. REC Ltd. (Rural Electrification Corporation), New Delhi is the Nodal Agency.
  • M/s REC has communicated sanction letter dated:11.05.2016 for DDUGJY Scheme with a project cost of Rs.282.87Crs includimg PMA charges.
  • As per the scheme guidelines, M/s. REC PDCL, New Delhi has appointed as PMA on 25.08.2015.
  • The Component-wise sanctioned Scheme cost to APEPDCL is as shown below:
Sl. No. Circle Rural Electrification (RE) System Strengthening SAGY Metering TOTAL
1 Srikakulam 20.15 27.83 0.17 0.08 48.23
2 Vizianagaram 16.8 18.81 0.28 0.08 35.97
3 Visakhapatnam 31.27 35.35 1.84 0.16 68.62
4 Rajamahendravaram 24.54 36.86 0.96 0.14 62.5
5 Eluru 13.85 51.14 1.01 0.14 66.14
  APEPDCL 106.61 169.99 4.26 0.6 281.46

 

DDUGJY SCHEME - PROGRESS OF WORKS IN APEPDCL AS ON 31.01.2018

Sl. No Name of the Work Unit Sanctioned Target (Awarded Quantity) Achieved (Completed Quantity) % of progress
1 New 33/11KV Outdoor Sub-stations Nos. 80 82 54 66%
2 33KV Line: New/Interlinking/Re-orientation Kms 511.70 519.65 374.45 72%
3 11KV Line: New/Interlinking/Re-orientation Kms 923.15 705.06 391.11 55%
4 LT Line: New/Interlinking/Re-orientation Kms 261.53 188.15 10.44 6%
5 6.3KV Line: New Kms 781.52 773.32 690.31 89%
6 LT Arial Bunched Cable Nos. 1445.73 1420.51 1356.21 95%
7 Installation of New/Augmentation of DTRs Nos. 2520 2475 2370 96%
8 Capacitor Bank Nos. 80 80 14 18%
9 Feeder meters Nos. 321 321 206 64%
10 Release of services (APL+BPL) Nos. 198195 198329 198329 100%
11 SAGY Villages Nos. 20 30 30 100%
12 Installation of Signboards Nos. 3108 3068 2134 70%
a At Villages Nos. 478 478 330 69%
b At Substations Nos. 80 86 47 55%
c At SAGY Villages Nos. 30 29 1 3%
d At DTRs Nos. 2520 2475 1756 71%

DDUGJY SCHEME - PROGRESS OF WORKS IN SRIKAKULAM CIRCLE AS ON 31.01.2018

Sl. No Name of the Work Unit Sanctioned Target (Awarded Quantity) Achieved (Completed Quantity) % of progress
1 New 33/11KV Outdoor Sub-stations Nos. 9 9 7 78%
2 33KV Line: New/Interlinking/Re-orientation Kms 72 83 57.26 69%
3 11KV Line: New/Interlinking/Re-orientation Kms 182.13 166.58 100.73 60%
4 LT Line: New/Interlinking/Re-orientation Kms 156.34 84.89 6.44 8%
5 6.3KV Line: New Kms 212.25 211.23 189.41 90%
6 LT Arial Bunched Cable Nos. 228.07 211.68 209.22 99%
7 Installation of New/Augmentation of DTRs Nos. 737 737 718 97%
8 Capacitor Bank Nos. 9 9 6 67%
9 Feeder meters Nos. 42 42 34 81%
10 Release of services (APL+BPL) Nos. 36227 36238 36238 100%
11 SAGY Villages Nos. 1 1 1 100%
12 Installation of Signboards Nos. 778 778 693 89%
a At Villages Nos. 31 31 13 42%
b At Substations Nos. 9 9 7 78%
c At SAGY Villages Nos. 1 1 1 100%
d At DTRs Nos. 737 737 672 91%

DDUGJY SCHEME - PROGRESS OF WORKS IN VIZIANAGARAM CIRCLE AS ON 31.01.2018

Sl. No Name of the Work Unit Sanctioned Target (Awarded Quantity) Achieved (Completed Quantity) % of progress
1 New 33/11KV Outdoor Sub-stations Nos. 11 10 7 70%
2 33KV Line: New/Interlinking/Re-orientation Kms 65.00 61.15 59.18 97%
3 11KV Line: New/Interlinking/Re-orientation Kms 56.57 58.04 46.65 80%
4 LT Line: New/Interlinking/Re-orientation Kms 13.76 13.54 0.00 0%
5 6.3KV Line: New Kms 130.16 147.52 114.71 78%
6 LT Arial Bunched Cable Nos. 158.31 152.80 125.95 82%
7 Installation of New/Augmentation of DTRs Nos. 349 397 323 81%
8 Capacitor Bank Nos. 11 11 1 9%
9 Feeder meters Nos. 44 44 28 64%
10 Release of services (APL+BPL) Nos. 34576 34736 34736 100%
11 SAGY Villages Nos. 4 8 8 100%
12 Installation of Signboards Nos. 393 439 174 40%
a At Villages Nos. 25 25 11 44%
b At Substations Nos. 11 10 0 0%
c At SAGY Villages Nos. 8 7 0 0%
d At DTRs Nos. 349 397 163 41%

DDUGJY SCHEME - PROGRESS OF WORKS IN VISAKHAPATNAM CIRCLE AS ON 31.01.2018

Sl. No Name of the Work Unit Sanctioned Target (Awarded Quantity) Achieved (Completed Quantity) % of progress
1 New 33/11KV Outdoor Sub-stations Nos. 19 18 16 89%
2 33KV Line: New/Interlinking/Re-orientation Kms 82.00 71.30 67.75 95%
3 11KV Line: New/Interlinking/Re-orientation Kms 194.99 77.00 69.80 91%
4 LT Line: New/Interlinking/Re-orientation Kms 17.80 17.80 0.00 0%
5 6.3KV Line: New Kms 216.06 218.19 218.19 100%
6 LT Arial Bunched Cable Nos. 392.29 421.94 396.55 94%
7 Installation of New/Augmentation of DTRs Nos. 374 344 344 100%
8 Capacitor Bank Nos. 19 19 7 37%
9 Feeder meters Nos. 85 85 56 66%
10 Release of services (APL+BPL) Nos. 52401 54027 54027 100%
11 SAGY Villages Nos. 2 7 7 100%
12 Installation of Signboards Nos. 742 715 642 90%
a At Villages Nos. 342 342 287 84%
b At Substations Nos. 19 22 16 73%
c At SAGY Villages Nos. 7 7 0 0%
d At DTRs Nos. 374 374 339 99%

DDUGJY SCHEME - PROGRESS OF WORKS IN RAJAMAHENDRAVARAM CIRCLE AS ON 31.01.2018

Sl. No Name of the Work Unit Sanctioned Target (Awarded Quantity) Achieved (Completed Quantity) % of progress
1 New 33/11KV Outdoor Sub-stations Nos. 18 22 11 50%
2 33KV Line: New/Interlinking/Re-orientation Kms 128.00 134.50 63.80 47%
3 11KV Line: New/Interlinking/Re-orientation Kms 164.30 200.27 57.92 29%
4 LT Line: New/Interlinking/Re-orientation Kms 47.31 47.31 2.00 4%
5 6.3KV Line: New Kms 140.36 144.88 140.36 97%
6 LT Arial Bunched Cable Nos. 432.58 454.96 445.36 98%
7 Installation of New/Augmentation of DTRs Nos. 738 713 701 98%
8 Capacitor Bank Nos. 18 18 0 0%
9 Feeder meters Nos. 76 76 40 53%
10 Release of services (APL+BPL) Nos. 45802 45373 45373 100%
11 SAGY Villages Nos. 7 7 7 100%
12 Installation of Signboards Nos. 839 818 506 62%
a At Villages Nos. 76 76 15 20%
b At Substations Nos. 18 22 11 50%
c At SAGY Villages Nos. 7 7 0 0%
d At DTRs Nos. 738 713 480 67%

 

DDUGJY SCHEME - PROGRESS OF WORKS IN ELURU CIRCLE AS ON 31.01.2018

Sl. No Name of the Work Unit Sanctioned Target (Awarded Quantity) Achieved (Completed Quantity) % of progress
1 New 33/11KV Outdoor Sub-stations Nos. 23 23 13 57%
2 33KV Line: New/Interlinking/Re-orientation Kms 164.70 169.70 126.46 75%
3 11KV Line: New/Interlinking/Re-orientation Kms 325.16 203.17 116.01 57%
4 LT Line: New/Interlinking/Re-orientation Kms 26.32 24.61 2.00 8%
5 6.3KV Line: New Kms 82.69 51.50 27.64 54%
6 LT Arial Bunched Cable Nos. 234.48 179.13 179.13 100%
7 Installation of New/Augmentation of DTRs Nos. 322 284 284 100%
8 Capacitor Bank Nos. 23 23 0 0%
9 Feeder meters Nos. 74 74 48 65%
10 Release of services (APL+BPL) Nos. 29189 27955 27955 100%
11 SAGY Villages Nos. 6 7 7 100%
12 Installation of Signboards Nos. 356 318 119 37%
a At Villages Nos. 4 4 4 100%
b At Substations Nos. 23 23 13 57%
c At SAGY Villages Nos. 7 7 0 0%
d At DTRs Nos. 322 284 102 36%