EASTEREN POWER DISTRIBUTION COMPANY OF A.P.LIMITED
CORPORATE OFFICE:VISAKHAPATNAM
E/S to Indl / Agl Works
List of officers who claimed Excess Bills
Sl. No Name of the Work Details of Excess Billing Excess Amount Claimed (In RS.) Name of the AE Name of the ADE/DE checkmeasured the Bill
1 Inspection of certain works in Rajahmundry Division in Rajahmundry Circle on 12-5-09 & 13-5-09 1) 0.10 KM of excess 11 KV Line executed.
2) Out of 10 Nos. PSCC poles drawn 7 Nos. only executed in the field.
3) 1 No. LT HG Fuse set drawn but not utilized.
4) Out of 3 Nos. PSCC poles drawn 2 Nos. only executed in the field.
5) 4 Nos. Stays were provided without bows.
D6/RJY= Rs.3190/- Sampath Nagaram/Section =Rs.38161/- Rajanagaram = Rs.1510/- Total:42861/- 1)Sri.B.Suryanarayana, Ex-AE/O/Rajanagaram (presently AE/CT Meters / Bommuru) 2)V.Srinivasu, AE/O/Kadiyam 3)B.Satyanarayana, AE/O/Dowleswaram 4)Y.V.S.Subrahmanyam, AE/O/D6/RJY 5)G.Ch.Rama Chandra Rao, Ex-AE/O/Sampathnagaram ( AE/O/ Ambajipeta) 1)Sri.S.Satya Sai Baba, ADE/O/Town-II/RJY 2)Sri.N.Samuel, ADE/O/Rural/RJY
2 Inspection of works pertaining to E/S to Agl services of Rangampeta Mandal under “Tatkal Scheme Meter Tariff” in Rangampeta Section of Jaggampeta Sub-Division in Jaggampeta Division on 4-07-2009 1) 8 M (300 Kgs / WL) PSCC Poles not erected but billed. 2)MS Stay set not provided but billed. 3) 11 KV Top cleats not provided but billed. 4) LT Cross arms not provided but billed. 5)LT AB Cable not laid but billed. 20407/- Sri.Ch.J.P.Narayana, Ex-AAE/O/Rangampeta (presentlyAAE/O/Payakaraopeta) Sri.P.Trinadha Rao, ADE/O/Jaggampeta
 
 